Breaking capacity is one of the most important ratings of a fuse, yet it is sometimes overlooked in favour of current rating alone. This overview explains what breaking capacity means and how it relates to the fault level of the installation.
1. What Breaking Capacity Means
Breaking capacity, also called interrupting rating, is the maximum prospective current that a fuse can safely interrupt under specified conditions. It is verified by type tests defined in the applicable product standard.
A fuse asked to interrupt a current above its breaking capacity may fail to clear the fault safely. The rating is therefore a safety-critical parameter, not a performance preference.
2. Prospective Short-Circuit Current
The prospective short-circuit current is the current that would flow at a point in the installation if a fault of negligible impedance occurred there. It depends on the supply source, transformer impedance, cable sizes and circuit length.
This value is normally obtained from a short-circuit calculation or from data provided by the supply utility. Every protective device in the circuit should have a breaking capacity at least equal to the prospective current at its location.
3. Current Limitation and Let-Through Energy
Many fuses are current-limiting: they clear a fault before the prospective current reaches its peak. This reduces both the peak let-through current and the energy passed to the circuit during the fault.
Lower let-through energy reduces stress on cables, busbars and connected equipment. When comparing fuse types, both the breaking capacity and the let-through characteristics should be considered.
A fuse with the correct current rating but inadequate breaking capacity does not protect the installation. Check both ratings against system data.
4. Applying the Rating in Practice
Breaking capacity is specified together with the rated voltage and the test circuit characteristics. A fuse tested under AC conditions is not automatically suitable for the same fault level in a DC circuit.
Where the installation fault level is uncertain, it should be determined before the protective device is finalized. When equipment is modified or the supply is upgraded, the fault level should be reviewed again.